Medium Voltage Projects

At PACK Power, we’re the epitome of reliability and excellence in the energy sector. Our highly technical team offers nationwide solutions for medium-voltage needs, emphasizing safety-driven construction and services. Our comprehensive approach ensures meticulous planning and execution for optimal performance and longevity.

Featured Projects

Our Projects

Medium Voltage Collection System on a 70MW Solar Project in Virginia. Contracted to provide procurement and construction services for an AC/DC system with 61,000 LF of MV trench in Virginia.

Medium Voltage Collection System on a 240MW Solar project in Louisiana. Contracted to provide services for 142,000 LF MV cable installation.

Medium Voltage Collection System on a 240MW Data Center project in Texas. Contracted to provide services for 36,000 LF MV cable installation and MV terminations of Substation Risers, Junction Boxes, and Transformers.

Lane City, TX
Completed: 2025
Customer: RWE
Megawatts: 202
Footage: 267,000

Paris, TX
Completed: 2025
Customer: Nexus
Megawatts: 171
Footage: 89,000

Installation of a 34.5kV collection system in Texas including MV cable supply, installation, and termination, inverter and junction box installation, and associated conduit and grounding to support a 175MWAC Solar project.

Installation of a 34.5kV collection system in Missouri including MV cable supply, installation, and termination, inverter and junction box installation, and associated conduit and grounding to support a 295MWAC Solar project.

Medium Voltage Collection System on a Solar project in New Mexico. This included supply and installation of junction boxes, 35 kV terminations, testing support, commissioning support, and DC cable stringing and terminations.

A temporary substation solution was needed to energize a new addition to an existing Wind Project. The scope included trenching in and terminating the new collection system to existing risers in the existing substation along with a modification of utility metering cabinet, and various other activities to support energization and testing.

Bell County, TX
Completed: 2024
Customer: X-Elio
Megawatts: 100
Footage: 45,000

Installation of a 34.5kV collection system including MV cable supply, installation, and termination, inverter and junction box installation, and associated conduit and grounding to support 100 MWAC.

Green Forest, AR
Completed: 2025
Customer: Scout Clean Energy
Megawatts: 183
Footage: 188,000

Spring Grove, VA
Completed: 2025
Customer: Urban Grid
Megawatts: 193
Footage: 187,000

Installation of a 34.5kV collection system in Virginia including MV cable supply, installation, and termination, inverter and junction box installation, and associated conduit and grounding to support a 150MWAC Solar project.

Herford, NC
Completed: 2024
Customer: Duke Energy
Megawatts: 189
Footage: 149,550

Bay City, TX
Completed: 2024
Customer: RWE
Megawatts: 151.2
Footage: 465,014

Parliament, TX
Completed: 2024
Customer: Parliament Solar
Megawatts: 483
Footage: 241,476

Rock River, WY
Completed: 2023
Customer: PacifiCorp
Megawatts: 
Footage: 37,890

Installation of 35 kV Collection System to support 19 Turbine Repower Wind Projects in Wyoming, including MV and LV cable installation and termination, transformer and junction box installation, and MET/ADLS electrical installations.

Shelley, ID
Completed: 2023
Customer: Clearway Energy Group
Megawatts: 159.8
Footage: 181,068

Tunica, MS
Completed: 2023
Customer: AES
Megawatts: 184.5
Footage: 178,826

Port Mansfield, TX
Completed: 2022
Customer: Apex Energy
Megawatts: 301.5
Footage: 284,074

Lakota, IA
Completed: 2021
Customer: Duke Energy
Megawatts: 207
Footage: 284,306

Mount Calm, TX
Completed: 2021
Customer: NextEra Energy Resources
Megawatts: 301.6
Footage: 669,226

Protales, NM
Completed: 2020
Customer: Xcel Energy
Megawatts: 522.8
Footage: 1,028,292

Fluvanna, TX
Completed: 2019
Customer: Tri Global Energy
Megawatts: 158
Footage: 200,000

Crocker, SD
Completed: 2019
Customer: National Grid Renewables
Megawatts: 209.4
Footage: 292,198

Petersburg, TX
Completed: 2019
Customer: Xcel Energy
Megawatts: 478
Footage: 494,922

Kulm, ND
Completed: 2019
Customer: Xcel Energy
Megawatts: 150
Footage: 75,056

Wildorado, TX
Completed: 2018
Customer: Macquarie
Megawatts: 200.1
Footage: 188,366

Vici, OK
Completed: 2018
Customer: Scout Clean Energy
Megawatts: 198.6
Footage: 281,912

Blue Hill, NE
Completed: 2018
Customer: NextEra Energy Resources
Megawatts: 85.1
Footage: 153,502

Fluvanna, NM
Completed: 2018
Customer: Akuo Energy
Megawatts: 30
Footage: 43,894

Fluvanna, NM
Completed: 2017
Customer: Tri Global Energy
Megawatts: 155.4
Footage: 243,730

Renfrow, OK
Completed: 2016
Customer: Apex Energy
Megawatts: 147.2
Footage: 56,118

Courtenay, ND
Completed: 2016
Customer: Xcel Energy
Megawatts: 200
Footage: 274,874

Blackwell, OK
Completed: 2016
Customer: Duke Energy
Megawatts: 193
Footage: 235,132

Rio Grande City, TX
Completed: 2015
Customer: Duke Energy
Megawatts: 200
Footage: 348,128

Rio Grande City, TX
Completed: 2015
Customer: Duke Energy
Megawatts: 110
Footage: 133,974

O’Donnell, TX
Completed: 2015
Customer: Mesa Power
Megawatts: 164.7
Footage: 245,028

Rio Grande City, TX
Completed: 2014
Customer: Duke Energy
Megawatts: 200
Footage: 407,737

O’Donnell, TX
Completed: 2014
Customer: Mesa Power
Megawatts: 211.2
Footage: 332,172

Gladbrook, IA
Completed: 2013
Customer: MidAmerican Energy
Megawatts: 43.7
Footage: 41,568

Rollag, MN
Completed: 2013
Customer: PRC
Megawatts: 48
Footage: 120,160

Vega, TX
Completed: 2012
Customer: EDF Renewables
Megawatts: 161
Footage: 237,694

Sebastian, TX
Completed: 2012
Customer: Duke Energy
Megawatts: 201.6
Footage: 224,394

Sebastian, TX
Completed: 2012
Customer: Duke Energy
Megawatts: 200.1
Footage: 179,307

Gary, KS
Completed: 2012
Customer: Duke Energy
Megawatts: 165.6
Footage: 248,660

Ford, KS
Completed: 2012
Customer: Duke Energy
Megawatts: 167.9
Footage: 294,498

Gary, KS
Completed: 2011
Customer: CVP Energy
Megawatts: 131.1
Footage: 230,884

American Falls, ID
Completed: 2011
Customer: Ridgeline Energy
Megawatts: 79.2
Footage: 175,000

Vega, TX
Completed: 2011
Customer: Cielo Wind Power
Megawatts: 73.6
Footage: 104,610

Dewey, OK
Completed: 2010
Customer: Edison Mission Energy
Megawatts: 129.6
Footage: 147,198

Petersburg, NE
Completed: 2010
Customer: Edison Mission Energy
Megawatts: 81
Footage: 152,072

Burlington, CO
Completed: 2010
Customer: Duke Energy
Megawatts: 51
Footage: 100,000

Baker, MT
Completed: 2009
Customer: MDU
Megawatts: 18
Footage: 10,000

Rhame, ND
Completed: 2009
Customer: MDU
Megawatts: 19.5
Footage: 30,000

Center, ND
Completed: 2009
Customer: NextEra Energy Resources
Megawatts: 49.5
Footage: 100,000

Adair, IA
Completed: 2008
Customer: MidAmerican Energy
Megawatts: 174.8
Footage: 250,000

Langdon, ND
Completed: 2008
Customer: NextEra Energy Resources
Megawatts: 40.5
Footage: 75,000

Wessington Springs, SD
Completed: 2008
Customer: Babcock and Brown
Megawatts: 51
Footage: 135,000

Contact us to learn more about our projects